The submitted Hunting Hawk proposal was reported withdrawn; that does not establish permanent abandonment of the site.
Glen Allen, Virginia · Research checked Check date not yet confirmed
Reported project facts
Reported; not independently confirmed by Radar. Source publication, retrieval and recheck dates: Not yet recorded.
Reported developer / operator
HHHunt Corporation
Location
Glen Allen, Virginia
Recorded stage
Withdrawn
The retained county announcement reports withdrawal of the submitted Hunting Hawk proposal. It does not establish permanent abandonment of all future uses at the site.
This is the reported stage in the retained source material, not a new confirmation of present conditions. A proposal, permission, construction phase and operating milestone are different claims. Check later decisions, withdrawals and changes before acting.
“Retrieved by Radar” is when we obtained the source for this review. “Source check” applies to the facts cited here. Neither date means the project itself changed.
Member research: available contractors and engineers, exact reported values and capacity evidence, detailed sources and permitting history, plus tracker CSV export. Availability and verification vary by record.
These dated records describe decisions and procedural steps. A hearing or lawsuit does not, on its own, establish a delay or a change in project stage.
County announces Hunting Hawk application withdrawal
Application withdrawal announced; exact withdrawal-letter date and later proposals unresolved.
Decision and source check
The January 29 county brief records the January 28 announcement that the proposed 400-acre Ashland Road data-center request had been withdrawn. January 28 is the announcement date; the exact withdrawal-letter date was not retrieved. This is not a final board denial or permanent abandonment of every future use. Capacity and imported acreage remain separately unverified.
Event type
Withdrawal announced
Deciding body
Hanover County Board of Supervisors announcement
Current disposition
Application withdrawal announced; exact withdrawal-letter date and later proposals unresolved.
Research checks and project milestones are tracked separately. Dates reflect publicly documented milestones. Projects may progress between public updates. Historical check dates retain their original research provenance. Recorded stage is a snapshot, not a guarantee of completion. How we research.