Upper Magnolia

Stage under review

Rezoning granted different permissions to the West tracts in May 2025; building permission and individual-phase outcomes remain unconfirmed.

Virginia · Research checked Check date not yet confirmed

Reported project facts

Reported; not independently confirmed by Radar. Source publication, retrieval and recheck dates: Not yet recorded.

Reported developer / operator
Google
Location
Chesterfield County, Virginia
Recorded stage
Stage under review

Known correction: the May 28, 2025 rezoning decision grants different permissions to Upper Magnolia West Tracts A and B. It does not establish a building permit, construction or the status of every phase.

This is the reported stage in the retained source material, not a new confirmation of present conditions. A proposal, permission, construction phase and operating milestone are different claims. Check later decisions, withdrawals and changes before acting.

Public supporting source (chesterfield.gov) ↗

“Retrieved by Radar” is when we obtained the source for this review. “Source check” applies to the facts cited here. Neither date means the project itself changed.

Member research: available contractors and engineers, exact reported values and capacity evidence, detailed sources and permitting history, plus tracker CSV export. Availability and verification vary by record.

Browse data center projects in Virginia · What does this recorded stage mean?

DOCUMENTED APPROVAL HISTORY

Documented approval history

These dated records describe decisions and procedural steps. A hearing or lawsuit does not, on its own, establish a delay or a change in project stage.

Upper Magnolia Green West Tract A and Tract B rezoning approved

Rezoning approved for the specified tracts; building permits and construction not established.

Decision and source check

The July 1, 2025 approval letter records the May 28 approval of case 25SN1038. Tract A permits data-center uses, while Tract B has separate industrial permissions. The case covers 979.23 acres; this does not establish a building permit, construction start, or the status of every Upper Magnolia phase.

Event type
Rezoning approved
Deciding body
Chesterfield County Board of Supervisors
Current disposition
Rezoning approved for the specified tracts; building permits and construction not established.
Source last checked
Oct 10, 2026

Chesterfield County approval letter, July 1, 2025, page 51 (opens in a new tab)