The record reports approved; Approved describes the matched zoning and conditional-use outcome, not issued building permission, a power agreement or physical construction.
Forsyth, Georgia · Research checked Check date not yet confirmed
Reported project facts
Reported; not independently confirmed by Radar. Source publication, retrieval and recheck dates: Not yet recorded.
Reported developer / operator
Trammell Crow Company
Location
Forsyth, Monroe County, Georgia
Recorded stage
Approved
Approved describes the matched zoning and conditional-use outcome, not issued building permission, a power agreement or physical construction. Keep the separate unmatched T5 lead distinct.
This is the reported stage in the retained source material, not a new confirmation of present conditions. A proposal, permission, construction phase and operating milestone are different claims. Check later decisions, withdrawals and changes before acting.
“Retrieved by Radar” is when we obtained the source for this review. “Source check” applies to the facts cited here. Neither date means the project itself changed.
Member research: available contractors and engineers, exact reported values and capacity evidence, detailed sources and permitting history, plus tracker CSV export. Availability and verification vary by record.
These dated records describe decisions and procedural steps. A hearing or lawsuit does not, on its own, establish a delay or a change in project stage.
Council approves agricultural rezoning and data-center conditional use
Council votes recorded; ordinance adoption documented March 2. Permits and construction unresolved.
Decision and source check
City minutes record unanimous rezoning of parcels 026 020, 015 005, 015 005A and 015 005B to Agricultural, plus a 5–1 conditional-use vote for data centers and substations on the H&H Timberlands campus. The minutes identify Trammell Crow’s representative. These are City of Forsyth, Monroe County actions, not Forsyth County near Cumming. They do not establish building permits or a construction start.
Event type
Rezoning and conditional use approved
Deciding body
City of Forsyth City Council
Current disposition
Council votes recorded; ordinance adoption documented March 2. Permits and construction unresolved.
Council adopts Forsyth Technology Campus ordinance at second reading
Zoning and conditional-use ordinance adopted; power agreement, permits and construction unresolved.
Decision and source check
March 2 minutes record unanimous ordinance approval at second reading, following the February 2 votes. The February conditions require a land-disturbance permit request within 36 months after executing a power-supply agreement; that period does not automatically begin on the vote date. Execution of that agreement, issued permits and physical construction have not been confirmed.
Event type
Ordinance adopted
Deciding body
City of Forsyth City Council
Current disposition
Zoning and conditional-use ordinance adopted; power agreement, permits and construction unresolved.
Research checks and project milestones are tracked separately. Dates reflect publicly documented milestones. Projects may progress between public updates. Historical check dates retain their original research provenance. Recorded stage is a snapshot, not a guarantee of completion. How we research.