FREE RESEARCH WORKSHEET · OCTOBER 19, 2026

Keep the claim attached to its evidence.

A repeatable worksheet for reporters, contractors, suppliers and research teams evaluating a data center project. Match the site and phase, retain the source wording, and make unresolved questions visible.

Download the blank worksheet (.md) ↓

This free download is a blank Markdown template you can edit in a text editor. It contains no project records, private contacts or member catalog export. Edition: October 19, 2026.

1. Match the site and phase

A nearby site, similar name or common developer does not establish that two records describe the same project.

  • Reported project name and aliases
  • Reported developer/operator and role (do not merge these roles)
  • City, county, state and responsible jurisdiction
  • Parcel or site identifier, if publicly documented
  • Campus, building or phase covered; evidence for the match

2. Keep one row per claim

Keep reported wording separate from your conclusion. A source check is not independent confirmation or a new project milestone. Use unknown when a date is not stated.

  • Claim and exact source wording
  • Public source URL, publisher and document/case identifier
  • Source publication date (or explicitly unknown)
  • Event/effective date stated by source (separate from publication)
  • Date you found the source; date you last checked it
  • Reported stage, role or capacity; geographic and phase scope
  • What the source establishes; what remains unknown
  • Later source, contradiction or correction and its public explanation

3. Separate hearings from decisions

A hearing notice or favorable recommendation does not establish final approval. A land-use decision alone does not establish construction, power availability or every environmental permission.

  • Authority, case number, site and scope
  • Application, notice, staff recommendation, hearing or adopted decision
  • Meeting date and agenda item; minutes, resolution or decision URL
  • Result, conditions and work authorized, quoting the instrument
  • Later withdrawal, denial, appeal, amendment or superseding action
  • Which permissions and jurisdictions still need checking

4. Preserve the capacity basis

Do not turn an up-to amount into delivered capacity, add overlapping phases, or equate electrical demand with IT load. If the basis is unclear, retain that uncertainty.

  • Source-qualified wording, range or category
  • Unit and basis: IT load, site power, utility demand or other
  • Per-building, phase, site or portfolio scope
  • Requested, proposed, contracted, energized or delivered
  • Forecast date and dependencies, if explicitly reported

5. Record the remaining business question

A named contractor or a project stage does not establish an open bid package, a buying contact or an available assignment.

  • Decision this evidence can support
  • Unresolved identity, stage, permission or team question
  • Next public source or responsible authority to check
  • Known contradiction disclosed alongside the claim
  • Researcher review date; separate editorial publication/update date

Citation and method limits

Suggested method citation: Data Center Radar, Data center project evidence worksheet, edition October 19, 2026, https://datacenterradar.com/research/data-center-project-evidence-worksheet, accessed [your access date].

Cite the original document for each project claim. Citing this worksheet does not substantiate a project's identity, status, capacity or approval. It is a research aid, not a national census, engineering assessment or complete list of required permissions. The edition date describes this worksheet, not a check of any project.

Record publication, event, discovery, source-check and editorial dates separately. Do not fill a missing date with today's date. Disclose known contradictions and corrections alongside the affected claim; do not quietly replace the earlier account. A missing search result leaves a question unresolved.

Use public sources for a public worksheet. Do not include private contact details or member-only evidence in a public copy. Third-party source documents retain their own reuse terms; this worksheet grants no rights to them.

Continue the research

FREE NATIONAL DIGEST

Follow U.S. data center development.

Get selected public project previews and practical research guidance from across the U.S. Sent when there are new previews to share, at most once a week. State-filtered email delivery is not currently available.

Get the free national digest →

Free to subscribe. Confirm your email to join.
Unsubscribe anytime.